Our Projects

Recent Experience and Performance

Provision of Solar Rehabilitation Activities Mininta

CLIENT: SPDC/Poseidon
LOCATION: Minita
DURATION: 25/05/2023 - 02/06/2023
STATUS: Completed

Provision of Solar Rehabilitation Activities Ogale

CLIENT: SPDC/Poseidon
LOCATION: Ogale
DURATION: 18/05/2023 - 22/05/2023
STATUS: Completed

Provision of Cathodic Protection Survey Soku

CLIENT: SPDC/Poseidon
LOCATION: Soku
DURATION: 06/05/2023 - 09/05/2023
STATUS: Completed

Provision of Cathodic Protection Survey Nun river

CLIENT: SPDC/MJD
LOCATION: Nun River, Diebu Creek
DURATION: 12/02/2023 - 16/02/2023
STATUS: Completed

40" DCVG Survey

CLIENT: SPDC/Poseidon
LOCATION: Soku ROW
DURATION: 07/05/2023 - 08/05/2023
STATUS: Completed

Anode and TP installation on 8" Ubie-Ukplede

CLIENT: SPDC/Norton
LOCATION: Ubie
DURATION: 03/04/2023 - 03/04/2023
STATUS: Completed

Provision of TP installation on 8" & 16" Gasline

CLIENT: SPDC/Melcurt
LOCATION: Yokri
DURATION: 04/05/2023 - 08/05/2023
STATUS: Completed

Cathodic Protection Survey

CLIENT: SPDC/MJD
LOCATION: Southbank, Forcados Terminal, Estuary
DURATION: 07/04/2023 - 11/04/2023
STATUS: Completed

Provision of Cathodic Protection Survey

CLIENT: SPDC/MJD
LOCATION: Otumara, Escravos, Nortbank, Yokri Forcados River
DURATION: 24/03/2023 - 17/04/2023
STATUS: Completed

Provision of Cathodic Protection Survey

CLIENT: SPDC/Poseidon
LOCATION: Tunu, Benesede, Ogbotobo, Brass creek, Opukushi
DURATION: 29/03/2023 - 13/04/2023
STATUS: Completed

Provision of Cathodic protection remedial Works

CLIENT: SPDC/Melcurt
LOCATION: Yokri
DURATION: 24/01/2023 - 29/01/2023
STATUS: Completed

Provision of Cathodic Protection Survey Kolocreek

CLIENT: SPDC/Poseidon
LOCATION: Kolo creek
DURATION: 26/01/2023 - 11/02/2023
STATUS: Completed

Provision of Cathodic Protection Survey Gbaran

CLIENT: SPDC/MJD
LOCATION: Gbaran District Node
DURATION: 29/01/2023 - 15/02/2023
STATUS: Completed

Provision of Cathodic Protection Survey Okordia

CLIENT: SPDC/Poseidon
LOCATION: Okordia, Adibawa, Ubie, Ukpelede
DURATION: 01/02/2023 - 05/02/2023
STATUS: Completed

Provision of UT/LRUT/ PAUT Inspections/Cleanup #15 Oben NAG Flowlines & Hook-up Arms

CLIENT: SEPLAT
LOCATION: Oben
DURATION: 26/01/2023 - 10/02/2023
STATUS: Completed

Provision UT/LRUT Verification of 5 Worst Defects identified by PDT on 8" Oben FS Pipeline

CLIENT: SEPLAT
LOCATION: Okwadede Village Amukpe
DURATION: 26/01/2023 - 08/02/2023
STATUS: Completed

PROVISION OF PHASED ARRAY ON 36" RUMUEKPE TO NKPOLU TL & NUN RIVER TO KOLO CREEK TL 23NOS POINTS

CLIENT: SPDC/MJD
LOCATION: Nun River To Kolo Creek
DURATION: 20/11/2022 - 31/12/2022
STATUS: Completed

PROVISION OF 4Q2022 LRUT/UT/PAUT INSPECTION OF #15 OBEN NAG FLOELINES AND HOOK-UP ARMS

CLIENT: SEPLAT Energy
LOCATION: Oben
DURATION: 10/11/2022 - 26/12/2022
STATUS: Completed

Provision of Solar Rehabilitation Activities Ibaa

CLIENT: SPDC/Poseidon
LOCATION: Ibaa MFD
DURATION: 05/03/2023 - 13/03/2023
STATUS: Completed

Provision of Solar Rehabilitation Activities Assa

CLIENT: SPDC/MJD
LOCATION: Assa MFD
DURATION: 26/03/2023 - 01/04/2023
STATUS: Completed



Some of our Field Works

Executed Projects